← Back to Shropshire

Energy sites / United Kingdom / Shropshire

Battery storage · United Kingdom

Hortonwood - Energy Storage Facility

Awaiting Construction0.2 MWChecked 6 October 2026Last changed in the dataset 25 July 2025

Technology
Battery storage (Stand-alone Storage)
Capacity
0.2 MW
Status
Awaiting Construction (Appeal Granted)
Operator or applicant
AMP Clean Energy
Location
Highway Verge Fronting Veolia I W M F, Hortonwood, 60 Hortonwood, Telford, Shropshire, TF1 7GY, United Kingdom
Planning authority
Telford and Wrekin
Planning application
TWC/2024/0835
Appeal reference
TWC/2024/0835

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 13 November 2024 Planning application submitted
  • 7 January 2025 Planning permission refused
  • 9 January 2025 Appeal lodged
  • 7 July 2025 Planning permission granted
  • 7 July 2025 Appeal granted
  • 7 July 2028 Planning permission expired

None found. The register holds no published incident that names Hortonwood - Energy Storage Facility. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.