← Back to Kent

Energy sites / United Kingdom / Kent

Battery storage · United Kingdom

Hornbeam Close - Micro Energy Storage

Awaiting Construction0.2 MWChecked 6 October 2026Last changed in the dataset 1 May 2026

Technology
Battery storage (Stand-alone Storage)
Capacity
0.2 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
AMP Clean Energy
Location
Se/O 1 Hornbeam Close, Ashford, Kent, TN23 3DY, United Kingdom
Planning authority
Ashford
Planning application
PA/2025/2127

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 17 November 2025 Planning application submitted
  • 9 March 2026 Planning permission granted
  • 9 March 2029 Planning permission expired

None found. The register holds no published incident that names Hornbeam Close - Micro Energy Storage. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.