← Back to Cheshire

Energy sites / United Kingdom / Cheshire

Battery storage · United Kingdom

Herrod Avenue, South Reddish - Battery Energy Storage

Application WithdrawnChecked 6 October 2026Last changed in the dataset 6 June 2024

Technology
Battery storage (Stand-alone Storage)
Status
Application Withdrawn (Planning Application Withdrawn)
Operator or applicant
Infra Balance New Energy Limited
Location
5 Herrod Avenue, South Reddish, Stockport, Cheshire, SK4 1QH, United Kingdom
Planning authority
Stockport
Planning application
DC/090561

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 7 December 2023 Planning application submitted
  • 5 June 2024 Application withdrawn

None found. The register holds no published incident that names Herrod Avenue, South Reddish - Battery Energy Storage. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 176 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.