← Back to West Midlands

Energy sites / United Kingdom / West Midlands

Battery storage · United Kingdom

Hams Hall - Battery Energy Storage System

Under Construction400 MWChecked 6 October 2026Last changed in the dataset 9 March 2026

Technology
Battery storage (Stand-alone Storage)
Capacity
400 MW
Status
Under Construction
Operator or applicant
Welbar Energy Storage Limited / Penso Power (BW ESS)
Location
East & Se/O Dunton Hall, Kingsbury Road, Curdworth, Sutton Coldfield, West Midlands, B76 0BL, United Kingdom
Planning authority
North Warwickshire
Planning application
PAP/2021/0473

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 5 August 2021 Planning application submitted
  • 4 March 2022 Planning permission granted
  • 1 January 2025 Construction started
  • 4 March 2025 Planning permission expired

None found. The register holds no published incident that names Hams Hall - Battery Energy Storage System. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 176 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.