← Back to Cumbria

Energy sites / United Kingdom / Cumbria

Battery storage · United Kingdom

Grassing Rome Street - Battery Storage

Awaiting Construction15.5 MWChecked 6 October 2026Last changed in the dataset 8 April 2024

Technology
Battery storage (Stand-alone Storage)
Capacity
15.5 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
STOR 141 Limited
Location
Former Railway Line and Bousteads Grassing, Rome Street, Carlisle, Cumbria, CA2 5AD, United Kingdom
Planning authority
Cumberland
Planning application
22/0513

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 28 June 2022 Planning application submitted
  • 7 March 2024 Planning permission granted
  • 7 March 2027 Planning permission expired

None found. The register holds no published incident that names Grassing Rome Street - Battery Storage. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents