← Back to West Glamorgan

Energy sites / United Kingdom / West Glamorgan

Battery storage · United Kingdom

Garngoch Industrial Estate, Penllergaer - Micro Energy Storage Facility

Awaiting Construction0.2 MWChecked 6 October 2026Last changed in the dataset 27 May 2025

Technology
Battery storage (Stand-alone Storage)
Capacity
0.2 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
AMP Clean Energy
Location
Unit 3, Garngoch Industrial Estate, Gorseinon Road, Penllergaer, West Glamorgan, SA4 9WF, United Kingdom
Planning authority
Swansea
Planning application
2025/0965/FUL

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 6 May 2025 Planning application submitted
  • 27 June 2025 Planning permission granted
  • 27 June 2030 Planning permission expired

None found. The register holds no published incident that names Garngoch Industrial Estate, Penllergaer - Micro Energy Storage Facility. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.