Eskrigg End Road, Old Hutton - Battery Energy Storage System

Awaiting Construction200 MWChecked 6 October 2026Last changed in the dataset 28 July 2025

Technology
Battery storage (Stand-alone Storage)
Capacity
200 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Harmony MS Limited
Location
South of Eskrigg End Road Old Hutton, Cumbria, LA8 0NU, United Kingdom
Planning authority
Westmorland and Furness
Planning application
2024/2413/FPA

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 4 October 2024 Planning application submitted
  • 10 July 2025 Planning permission granted
  • 10 July 2030 Planning permission expired

None found. The register holds no published incident that names Eskrigg End Road, Old Hutton - Battery Energy Storage System. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 176 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.