← Back to Surrey

Energy sites / United Kingdom / Surrey

Battery storage · United Kingdom

Dorking Battery Energy Storage System

Operational6 MWChecked 6 October 2026Last changed in the dataset 31 July 2020

Technology
Battery storage (Stand-alone Storage)
Capacity
6 MW
Status
Operational
Operator or applicant
Grid Battery Storage (GBSL)
Location
Milton Court Farm, Milton Court Lane, Dorking, Surrey, RH4 3LY, Surrey, RH4 3LY, United Kingdom
Planning authority
Mole Valley
Planning application
MO/2016/1168
First operating
2020

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 20 July 2016 Planning application submitted
  • 15 January 2017 Construction started
  • 31 July 2020 Operational

None found. The register holds no published incident that names Dorking Battery Energy Storage System. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.