Dogger Bank A & B (was Creyke Beck A & B)

Under Construction2400 MWChecked 6 October 2026Last changed in the dataset 12 April 2022

Technology
Offshore wind
Capacity
2400 MW
Status
Under Construction
Operator or applicant
SSE/Equinor (formerly Statoil, formerly Forewind)
Location
125km off coast of Yorkshire, Offshore, United Kingdom
Planning authority
The Planning Inspectorate - National Infrastructure
Planning application
EN010021
Turbines
190, 260 m to tip

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 29 August 2013 Planning application submitted
  • 17 February 2015 Planning permission granted
  • 17 February 2020 Planning permission expired
  • 1 July 2021 Construction started

None found. The register holds no published incident that names Dogger Bank A & B (was Creyke Beck A & B). If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at offshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at offshore wind farms

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.