← Back to Warwickshire

Energy sites / United Kingdom / Warwickshire

Battery storage · United Kingdom

Crimscote Solar Farm and Storage Project

Under ConstructionChecked 6 October 2026Last changed in the dataset 6 August 2024

Technology
Battery storage (Co-located with RE)
Status
Under Construction
Operator or applicant
Regener8 SPV1 Limited
Location
Crimscote WimpstoneView, Warwickshire, CV37 8UF, United Kingdom
Planning authority
Stratford-on-Avon
Planning application
21/02017/FUL

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 18 June 2021 Planning application submitted
  • 29 November 2022 Planning permission granted
  • 1 July 2024 Construction started
  • 29 November 2025 Planning permission expired

None found. The register holds no published incident that names Crimscote Solar Farm and Storage Project. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 176 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.