Battery storage · United Kingdom

Addlestone Moor, Chertsey Road - Micro Energy Storage System

Awaiting Construction0.2 MWChecked 6 October 2026Last changed in the dataset 24 February 2026

Technology
Battery storage (Stand-alone Storage)
Capacity
0.2 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
AMP Clean Energy
Location
The end of Addlestone Moor, by Chertsey Road, Surrey, KT15 2QJ, United Kingdom
Planning authority
Runnymede
Planning application
RU.25/1752

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 1 December 2025 Planning application submitted
  • 30 January 2026 Planning permission granted
  • 30 January 2029 Planning permission expired

None found. The register holds no published incident that names Addlestone Moor, Chertsey Road - Micro Energy Storage System. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.