← Back to Lancashire

Energy sites / United Kingdom / Lancashire

Battery storage · United Kingdom

Whitegate Battery Storage

Under Construction57 MWChecked 6 October 2026Last changed in the dataset 14 October 2025

Technology
Battery storage (Stand-alone Storage)
Capacity
57 MW
Status
Under Construction
Operator or applicant
Pelagic Energy (Constantine Energy)
Location
The National Grid Station, Broadgate, Chadderton, Oldham, Lancashire, OL9 9XA, United Kingdom
Planning authority
Oldham
Planning application
FUL/348501/22

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 14 February 2022 Planning application submitted
  • 19 May 2022 Planning permission granted
  • 1 October 2023 Construction started
  • 19 May 2025 Planning permission expired

None found. The register holds no published incident that names Whitegate Battery Storage. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.