Walpole Sub Station, Walpole Bank - Battery Storage

Operator Henry Energy Limited

Awaiting Construction100 MWData checked 16 November 2026Source record dated 24 February 2026

Watch this siteIts outage notices and incidents, what it earns and where it ranks, in your workspace and by email. 7 days free, no card.

Walpole Sub Station, Walpole Bank - Battery Storage is a 100 MW battery storage site 7.4 km north-east of Wisbech, Cambridgeshire, United Kingdom. Its planning application (22/02021/F) went to King's Lynn and West Norfolk on 8 November 2022 and was granted on 4 July 2023. Its status in the Renewable Energy Planning Database (UK government) is awaiting construction. There are 44 other energy sites within 10 km, 21 of them battery storage sites (hybrid battery and solar sites included). The register holds no incident at this site. It holds 14 incidents at battery storage sites (hybrid battery and solar sites included) in the United Kingdom, and 199 worldwide.

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack for Walpole Sub Station, Walpole Bank - Battery Storage sets out every comparable incident for this project, with sources. £295, by email in minutes; the order form arrives filled in from this record.

Get the evidence pack for this site, £295 See a sample pack (PDF)

The pack for this site lists 5 comparable battery incidents in the United Kingdom, grid-scale only, nearest first. The nearest is EIR-0584, Fire in a battery container at Rufford Colliery BESS, Rainworth; owner attributes it to a short circuit in NMC cells, 99 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-05842026Fire in a battery container at Rufford Colliery BESS, Rainworth; owner attributes it to a short circuit in NMC cells99 kmSignificant
EIR-01092025Fire in single battery unit at Thurrock BESS under construction139 kmSignificant
EIR-00582025Fire in two battery containers at Cirencester Hybrid Solar Farm, Gloucestershire184 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 2 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack
Technology
Battery storage (Stand-alone Storage)
Capacity
100 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Henry Energy Limited
Location
Opposite Walpole Sub Station Walpole Bank Walpole St Andrew, Cambridgeshire, PE14 7HZ, United Kingdom
Planning authority
King's Lynn and West Norfolk
Planning application
22/02021/F

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for 22/02021/F, with what the planning evidence pack adds for this site.

Every application in King's Lynn and West Norfolk · Alerts for applications and incidents near here

  • 8 November 2022 Planning application submitted
  • 4 July 2023 Planning permission granted
  • 4 July 2026 Planning permission expired

None found. The register holds no published incident that names Walpole Sub Station, Walpole Bank - Battery Storage. If you know of one, report it (confidential reports are anonymised).

Has Walpole Sub Station, Walpole Bank - Battery Storage had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Walpole Sub Station, Walpole Bank - Battery Storage; it holds 14 incidents at battery storage sites (hybrid battery and solar sites included) in the United Kingdom.
What is the status of Walpole Sub Station, Walpole Bank - Battery Storage?
Awaiting Construction, in the Renewable Energy Planning Database (UK government), where it last changed on 24 February 2026.
Where is Walpole Sub Station, Walpole Bank - Battery Storage?
7.4 km north-east of Wisbech, Cambridgeshire, United Kingdom (postcode PE14 7HZ).

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).