Land South of The Rayleigh Main Substation Battery Storage (Southend Arterial Road - Battery Energy Storage)

Operator Enso Green Holdings Limited · Owner Gresham House Devco Pipeline Limited

Application SubmittedData checked 16 November 2026Source record dated 13 March 2024

Watch this siteIts outage notices and incidents, what it earns and where it ranks, in your workspace and by email. 7 days free, no card.

Land South of The Rayleigh Main Substation Battery Storage (Southend Arterial Road - Battery Energy Storage) is a battery storage site 3 km west of Rayleigh, Essex, United Kingdom. Its planning application (24/00142/FULL) went to Basildon on 9 February 2024. Its status in the Renewable Energy Planning Database (UK government) is application submitted. There are 74 other energy sites within 10 km, 35 of them battery storage sites (hybrid battery and solar sites included). The register holds no incident at this site. It holds 14 incidents at battery storage sites (hybrid battery and solar sites included) in the United Kingdom, and 199 worldwide.

ENSO GREEN HOLDINGS LIMITED (12153574), active, since 2019. No outstanding charges on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.

Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack for Land South of The Rayleigh Main Substation Battery Storage (Southend Arterial Road - Battery Energy Storage) sets out every comparable incident for this project, with sources. £295, by email in minutes; the order form arrives filled in from this record.

Get the evidence pack for this site, £295 See a sample pack (PDF)

The pack for this site lists 5 comparable battery incidents in the United Kingdom, grid-scale only, nearest first. The nearest is EIR-0109, Fire in single battery unit at Thurrock BESS under construction, 16 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-01092025Fire in single battery unit at Thurrock BESS under construction16 kmSignificant
EIR-00582025Fire in two battery containers at Cirencester Hybrid Solar Farm, Gloucestershire172 kmSignificant
EIR-05842026Fire in a battery container at Rufford Colliery BESS, Rainworth; owner attributes it to a short circuit in NMC cells205 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 2 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack
Technology
Battery storage (Stand-alone Storage)
Status
Application Submitted (Planning Application Submitted)
Operator or applicant
Enso Green Holdings Limited
Owner
Gresham House Devco Pipeline Limited
Location
N/O Southend Arterial Road (A127), Wickford, Essex, SS12 9JQ, United Kingdom
Planning authority
Basildon
Planning application
24/00142/FULL

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for 24/00142/FULL, with what the planning evidence pack adds for this site.

Every application in Basildon · Alerts for applications and incidents near here

  • 9 February 2024 Planning application submitted

None found. The register holds no published incident that names Land South of The Rayleigh Main Substation Battery Storage (Southend Arterial Road - Battery Energy Storage). If you know of one, report it (confidential reports are anonymised).

Has Land South of The Rayleigh Main Substation Battery Storage (Southend Arterial Road - Battery Energy Storage) had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Land South of The Rayleigh Main Substation Battery Storage (Southend Arterial Road - Battery Energy Storage); it holds 14 incidents at battery storage sites (hybrid battery and solar sites included) in the United Kingdom.
What is the status of Land South of The Rayleigh Main Substation Battery Storage (Southend Arterial Road - Battery Energy Storage)?
Application Submitted, in the Renewable Energy Planning Database (UK government), where it last changed on 13 March 2024.
Where is Land South of The Rayleigh Main Substation Battery Storage (Southend Arterial Road - Battery Energy Storage)?
3 km west of Rayleigh, Essex, United Kingdom (postcode SS12 9JQ).

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).