← Back to Hertfordshire

Energy sites / United Kingdom / Hertfordshire

Battery storage · United Kingdom

Rush Green Motors - Battery storage

Revised50 MWChecked 6 October 2026Last changed in the dataset 14 March 2024

Technology
Battery storage (Stand-alone Storage)
Capacity
50 MW
Status
Revised
Operator or applicant
RNA Energy limited
Location
Rush Green Motors, London Road, Langley, Hitchin, Hertfordshire, SG4 7PQ, United Kingdom
Planning authority
North Hertfordshire
Planning application
21/01860/FP

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 15 June 2021 Planning application submitted
  • 6 October 2021 Planning permission granted
  • 6 October 2024 Planning permission expired

None found. The register holds no published incident that names Rush Green Motors - Battery storage. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.