Model Farm

Awaiting Construction49.9 MWChecked 6 October 2026Last changed in the dataset 24 February 2022

Technology
Battery storage (Stand-alone Storage)
Capacity
49.9 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Tribus Clean Energy
Location
Model Farm, Frenchs Road, Walpole St. Andrew, Wisbech, Cambridgeshire, PE14 7JF, United Kingdom
Planning authority
King's Lynn and West Norfolk
Planning application
21/01715/FM

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 31 August 2021 Planning application submitted
  • 27 January 2022 Planning permission granted
  • 27 January 2025 Planning permission expired

None found. The register holds no published incident that names Model Farm. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 176 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.