← Back to Merseyside

Energy sites / United Kingdom / Merseyside

Battery storage · United Kingdom

Hawthorne Road

Under Construction20 MWChecked 6 October 2026Last changed in the dataset 30 September 2020

Technology
Battery storage (Stand-alone Storage)
Capacity
20 MW
Status
Under Construction
Operator or applicant
Bluefield Renewable Developments
Location
491 Linacre Lane, Bootle, Merseyside, Merseyside, L20 5AL, United Kingdom
Planning authority
Sefton
Planning application
DC/2020/00085

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 29 January 2020 Planning application submitted
  • 29 March 2022 Planning permission granted
  • 14 April 2023 Planning permission expired

None found. The register holds no published incident that names Hawthorne Road. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.