← Back to Gloucestershire

Energy sites / United Kingdom / Gloucestershire

Battery storage · United Kingdom

Gloucestershire Science And Technology Par - Energy Storage Facility

Awaiting ConstructionChecked 6 October 2026Last changed in the dataset 14 March 2022

Technology
Battery storage (Stand-alone Storage)
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Ecotricity Berkeley Storage Limited
Location
Berkeley Green UTC Gloucestershire Science And Technology Park Hamfield Lane Berkeley, Gloucestershire, GL13 9FB, United Kingdom
Planning authority
Stroud
Planning application
S.22/0352/FUL

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 21 February 2022 Planning application submitted
  • 5 October 2022 Planning permission granted
  • 5 October 2025 Planning permission expired

None found. The register holds no published incident that names Gloucestershire Science And Technology Par - Energy Storage Facility. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 176 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.