Chleansaid Onshore Wind Farm

Awaiting Construction20 MWChecked 6 October 2026Last changed in the dataset 9 January 2024

Technology
Battery storage (Co-located with RE)
Capacity
20 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
ESB
Location
Dalnessie Estate, approximately 13 km northeast of Lairg, Highland, United Kingdom
Planning authority
Scottish Government (S36)
Planning application
ECU00002031

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 30 March 2022 Planning application submitted
  • 15 December 2023 Planning permission granted
  • 15 December 2026 Planning permission expired

None found. The register holds no published incident that names Chleansaid Onshore Wind Farm. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.