Planning pack for this site, £295Other options

Battery storage · United Kingdom

Albrighton Substation, Beamish Lane - Battery Storage

Operator Fig Power (part of Hydrock)

Awaiting Construction7 MWData checked 16 November 2026Source record dated 4 March 2024

Watch this siteIts outage notices and incidents, what it earns and where it ranks, in your workspace and by email. 7 days free, no card.

Albrighton Substation, Beamish Lane - Battery Storage is a 7 MW battery storage site on the edge of Codsall, West Midlands, United Kingdom. Its planning application (23/04541/FUL) went to Shropshire on 2 November 2023 and was granted on 26 February 2024. Its status in the Renewable Energy Planning Database (UK government) is awaiting construction. There are 57 other energy sites within 10 km, 25 of them battery storage sites (hybrid battery and solar sites included). The register holds no incident at this site. It holds 14 incidents at battery storage sites (hybrid battery and solar sites included) in the United Kingdom, and 199 worldwide.

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack for Albrighton Substation, Beamish Lane - Battery Storage sets out every comparable incident for this project, with sources. £295, by email in minutes; the order form arrives filled in from this record.

Get the evidence pack for this site, £295 See a sample pack (PDF)

The pack for this site lists 5 comparable battery incidents in the United Kingdom, grid-scale only, nearest first. The nearest is EIR-0584, Fire in a battery container at Rufford Colliery BESS, Rainworth; owner attributes it to a short circuit in NMC cells, 93 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-05842026Fire in a battery container at Rufford Colliery BESS, Rainworth; owner attributes it to a short circuit in NMC cells93 kmSignificant
EIR-06382020Explosion and prolonged fire at Orsted battery storage site in Liverpool95 kmMajor
EIR-00582025Fire in two battery containers at Cirencester Hybrid Solar Farm, Gloucestershire105 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 2 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack
Technology
Battery storage (Stand-alone Storage)
Capacity
7 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Fig Power (part of Hydrock)
Location
North of Albrighton Substation, Beamish Lane, Albrighton, West Midlands, WV8 1RH, United Kingdom
Planning authority
Shropshire
Planning application
23/04541/FUL

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for 23/04541/FUL, with what the planning evidence pack adds for this site.

Every application in Shropshire · Alerts for applications and incidents near here

  • 2 November 2023 Planning application submitted
  • 26 February 2024 Planning permission granted
  • 26 February 2027 Planning permission runs out

None found. The register holds no published incident that names Albrighton Substation, Beamish Lane - Battery Storage. If you know of one, report it (confidential reports are anonymised).

Has Albrighton Substation, Beamish Lane - Battery Storage had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Albrighton Substation, Beamish Lane - Battery Storage; it holds 14 incidents at battery storage sites (hybrid battery and solar sites included) in the United Kingdom.
What is the status of Albrighton Substation, Beamish Lane - Battery Storage?
Awaiting Construction, in the Renewable Energy Planning Database (UK government), where it last changed on 4 March 2024.
Where is Albrighton Substation, Beamish Lane - Battery Storage?
On the edge of Codsall, West Midlands, United Kingdom (postcode WV8 1RH).

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).