Wind (onshore)Croatia2017

Wind turbine collapses in high winds at Ravne 1 wind farm, Pag island

EIR-0830

Other entries that name Ravne

Provisional entry. Published from first reports. This entry is rechecked automatically and updated when more sources appear. Next update: 17 September 2026.

One of seven wind turbines at the Ravne 1 wind farm on the island of Pag, Croatia, collapsed after the island was hit by a strong north-easterly bura wind reported to be blowing at around 100 kilometres per hour. The turbine, described as 50 metres high and weighing 35 tonnes, came down and it is assumed that one blade broke first, with the 25 metre blade reported to have been thrown some hundred metres away by centrifugal force. The loss of the blade is thought to have unbalanced the machine while the other two blades were still rotating, leading to the collapse. The operator, Vjetroelektrane Pag, said the exact cause was yet to be determined. The other turbines at the site were reported undamaged and damage was put at EUR 600,000. The wind farm, commissioned in 2004 and described as Croatia's first commercial wind farm, has a capacity of 5.95 MW and comprises seven Vestas 850 kW turbines. It is owned by Adria Wind Power. No injuries were mentioned in reporting.

High local winds coincided with the failure, and an initial blade failure is assumed by local media and the broadcaster HRT to have caused an imbalance that led to the collapse. Vjetroelektrane Pag, the company in charge of the wind farm, said the cause was still to be determined, and no formal investigation findings are reported. The operator noted that such weather is not unusual for Pag.

  1. Turbines sited in areas prone to strong, recurring local wind events should have blade and structural designs and inspection regimes validated against those conditions.
  2. A single blade failure can escalate into a full structural collapse through rotor imbalance, which supports the value of vibration and imbalance detection able to trigger automatic shutdown.
  3. After a single-unit failure, blades and structural components on sister turbines at the same site should be inspected to rule out a common cause.

Published 2026-09-15. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.

Get the next one like this

One email when a newly reported incident is confirmed, at most two a day, plus a Monday digest. Free, no account needed, unsubscribe in one click.

By subscribing you agree to the privacy policy.

Related incidents

Wind (onshore) incidents in Croatia: 2 entries, with a free alert for the next one.

Browse the full register or submit an incident.